Main Content

Displaying 28 Document(s)

Summary of a meeting between staff from the Review Board and GNWT.

Information requests and the developer's responses were submitted using the Online Review System. This is a link to the ORS. 

Imperial Oil requested an extension to respond to parties' information requests to March 17, 2025.  The Review Board grants this extension. 

A request by Imperial to extend the response deadline by one week to respond to parties' information requests. 

This Notice of Proceeding describes the Review Board's rules of procedure related to information requests. 

A letter from CIRNAC announcing the approval of participant funding. 

The developer has submitted the Summary Impact Statement (SIS). The SIS includes this document, the Project Summary, along with appendices A - Q which will be posted separately. 

This is Appendix N of the Summary Impact Statement. 

This is Appendix M of the Summary Impact Statement. 

This is Appendix L of the Summary Impact Statement. 

This is Appendix K of the Summary Impact Statemetn. 

This is Appendix J of the Summary Impact Statement. 

This is Appendix I of the Summary Impact Statement. 

This is Appendix G of the Summary Impact Statement. 

This is appendix c of the Summary Impact Statement

This is appendix B of the Summary Impact Statement

This is appendix A, Figures 1-2, of the summary Impact Statement, 

The developer has submitted the Summary Impact Statement. Parties are invited to review this information and submit Information Requests by Feb 24, 2025.  

An updated workplan is attached. 

 

The Review Board will update and distribute an updated workplan when the developer provides the Summary Impact Statement.
The Developer is requesting an extension for the submission of the Summary Impact Statement to January 31, 2025.
This Notice of Proceedings describes the first round of information requests. Information requests are due Feb 7, 2025.