May 8, 2025 update- This proceeding has been adjourned at the developer's request.
Imperial Oil NWT Ltd. proposes to use Horizontal Directional Drilling (HDD) to replace a broken flowline between Goose and Bear Islands at its Norman Wells Operations. This flowline is required to allow for continued oil and gas production for a third of the oil and gas field.
An update from Imperial regarding the adjournment of the EA
Letter to Imperial Oil NWT Ltd. from the Review Board that includes the Board's decision on adjournment with reasons.
Staff discussed Imperials letters and procedural issues around the Line 490 Replacement environmental assessment (EA2425-01) and its relationship to the Norman Wells Operations EA (EA2425-02).
An update from Imperial regarding the adjournment of the EA
Letter to Imperial Oil NWT Ltd. from the Review Board that includes the Board's decision on adjournment with reasons.
Letter from the Government of the Northwest Territories in response to Imperial's request for adjournment.
Letter from the K’ahsho Got’ine Committee in response to Imperial's request for adjournment.
Notice of Proceeding from the Review Board regarding the process for considering Imperial's request to adjourn
The Délın̨ ę Ɂehdzo Got’ın̨ ę (Deline Renewable Resources Council) submission for the public hearing phase of the EA
Summary of a meeting between staff from the Review Board and GNWT.
Request for ruling from Imperial Oil NWT Ltd to adjourn the proceeding. The Review Board will meet to consider this request and provide a response as soon as possible.
This is the Délı̨nę Got’ı̨nę Government's written intervention for the public hearing phase of the EA
This is the GNWT's written submission for the hearing phase of the EA.
This is the Government of Canada's written intervention for the public hearing phase of the EA.
The Gwich'in Tribal Council submission for the public hearing phase of the EA.
This is the Ɂehdzo Got’ı̨nę Gots’ę́ Nákedı (Sahtu Renewable Resource Board) written intervention for the public hearing phase of the EA.
The Review Board grants KGC's extension request for submitting its written intervention until May 9, 2025.
The Review Board held a pre-hearing conference on April 23 to discuss the Hearing Phase of the EA. This document is a summary of the meeting.
A list of intervenors for the public hearings
The Review Board's presentation for the pre-hearing conference.
This is the agenda for the pre-hearing conference held on April 23, 2025.
The Review Board will hold a pre-hearing conference on April 23, 2025. The developer and parties who intend to intervene to this EA are requested to join Review Board staff to discuss preparing for the public hearings
| New | Total | Stage |
|---|---|---|
| 28 | Preliminary screening | |
| 25 | Assessment/review startup | |
| 6 | Scoping | |
| 4 | Terms of Reference and workplans | |
| 1 | Developer's Assessment Report/Environmental Impact Statement | |
| 28 | Information requests | |
| Technical or community sessions | ||
| Technical reports | ||
| 23 | Public hearings (current stage) | |
| Hearing follow-up | ||
| Report of Environmental Assessment/Impact Review | ||
| Post Report materials | ||
| Minister's decision and final measures | ||
| 1 | Other public registry materials | |
| 0 | 116 | Total Documents (See All) |