The GNWT proposes to construct an all weather gravel highway along the Mackenzie Valley bewteen Wrigley and Norman Wells.The route mostly follows the existing winter road. Approximately 281 km of new highway will be built from Hodgson Creek (located approximately 1 km north of Wrigley) to Prohibition Creek (located approximately 28 km southeast of Norman Wells).Bridges for the all-season route have already been constructed, except for the Bear River bridge. This bridge is already permitted and licensed separately.
A letter from MLA McNeely to the Mackenzie Valley Review Board about the EA process.
This is a letter from PKFN and the GNWT to MVEIRB about an update to the route of the proposed MVH.
This is a letter from the GNWT to MVEIRB regarding engagement on the DAR addenda timeline. Due to technical issues, this letter was only received by MVEIRB on January 29, 2026.
The Review Board and GNWT met on December 19, 2025 to discuss the environmental assessment process.
This is a letter from the GNWT to ADKFN in response to ADKFN's August 15th letter (PR#399)
This note to file describes conversation between PKFN and MVEIRB staff on Dec. 16.
GNWT and MVEIRB met on November 5 to discuss the environmental assessment process.
Letter from Daniel McNeely (MLA, Sahtu) to Catherine Fairbairn (MVEIRB) about the GNWT's 10 month extension request.
A letter from the Review Board to the GNWT, requesting that the GNWT respond to the concerns raised about the GNWT's extension request.
Letter from Charles McNeely (SSI) to Catherine Fairbairn (MVEIRB) about the GNWT's 10 month extension request.
A notice of proceeding granting the GNWT's extension request to July 31, 2026 for submission of the DAR addendum.
10 months extension request for submission of the Mackenzie Valley Highway Developer’s Assessment Report Addendum.
Joint letter providing an update on engagement between the Government of the Northwest Territories and Pehdzéh Kı̨́ First Nation.
This note to file describes a meeting between Review Board staff and CANNOR and GNWT PAB staff to discuss recent confidential information submissions.
Parties can view Łı́ı́dlı̨ı̨ Kų́ę́ First Nation's Confidential Information via an agreement with the Review Board. A non-confidential summary of the Confidential Information is on the public registry.
Public summary of the confidential Indigenous Knowledge document submitted by Łı́ı́dlı̨ı̨ Kų́ę́ First Nation.
A letter from Acho Dene Koe First Nation to the GNWT about the mitigation options summary table.
A report describing the results of a community survey completed in June 2025 by the Fort Norman Metis Community on behalf of the Tulita MVH Working Group.
A notice of proceeding granting the GNWT's extension request.
| New | Total | Stage |
|---|---|---|
| 5 | Preliminary screening | |
| 16 | Assessment/review startup | |
| 17 | Scoping | |
| 30 | Terms of Reference and workplans | |
| 116 | Developer's Assessment Report/Environmental Impact Statement | |
| 182 | Information requests (current stage) | |
| 46 | Technical or community sessions | |
| Technical reports | ||
| Public hearings | ||
| Hearing follow-up | ||
| 1 | Report of Environmental Assessment/Impact Review | |
| Post Report materials | ||
| Minister's decision and final measures | ||
| 2 | Other public registry materials | |
| 0 | 415 | Total Documents (See All) |