Sahtu Unconventional Oil Project - EA1213-01 Go to Project
Environmental Assessment (EA) - Withdrawn
This letter from Environment Canada confirms receipt of notification pursuant to ss. 79(1) of the Species at Risk Act (SARA).
Gahcho Kue Diamond Mine - EIR0607-001 Go to Project
Environmental Impact Review (EIR) - Complete
DRAFT Gahcho Kue Hearing Agenda
(555.25 Ko)
Meeting Minutes GNWT - De Beers
(258.76 Ko)
GNWT Technical Report
(481.56 Ko)
Tlicho Government Technical Report
(498.75 Ko)
Invitation to parties and agenda for the pre-hearing conference scheduled for November 1st from 1:30 - 4 pm.
EC Technical Report
(885.71 Ko)
Nechalacho Rare Earth Element Project - EA1011-001 Go to Project
Environmental Assessment (EA) - Complete
This is the Board's response to the Town of Hay River's letter dated October 23th, 2012.
This is the Board's response to MLA Hawkins letter dated October 18th, 2012.
Letter MVRB to NWT CofC re Avalon EA Oct 29 2012
(135.41 Ko)
The following document is a letter from the Review Board to Avalon Rare Metals Inc. regarding Avalon's response to second round information requests and next steps.
Giant Mine Remediation Project - EA0809-001 Go to Project
Environmental Assessment (EA) - Complete
SSP WL Cover Letter to Parties
(50.49 Ko)
Emergency Spill Response Plan
(2.56 Mo)
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
Arsenic Procedures
(236.11 Ko)
Giant Mine Dist List (MVLWB).docx
(32.16 Ko)
FTP Site Instructions
(11.7 Ko)
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
This is one of a series of documents from AANDC regarding emergency work on the roaster and underground stabilization at the Giant mine site.
Draft Combined WL Application Form 22Oct2012
(88.84 Ko)
AQMP for Roaster 22Oct2012
(121.04 Ko)
NICO Project - EA0809-004 Go to Project
Environmental Assessment (EA) - Complete
Closure of the public record
(255.25 Ko)
Fortune Minerals Closing Comments
(1.39 Mo)
Letter from Leon Lafferty
(577.89 Ko)