Main Content
Primary tabs
Results
Displaying 4901 - 4925 of 12202
Diamond Exploration - EA1112-001 Go to Project
Environmental Assessment (EA) - Complete
Note to File - July 13 Site Visit
(240.14 KB)
This is an updated Mineral Claim Sheet Map submitted by Alex Debogorski to the Review Board on July 20th.
Note to File - road conditions to Dettah
(185.89 KB)
This is a letter from the Yellowknives Dene First Nation dated July 15th, providing comments about the community information session stage.
This is a note to file about the transfer of evidence to the public registry for EA 1112-001
This is an Information Request to the Prince of Wales Northern Heritage Centre from the Review Board.
Giant Mine Remediation Project - EA0809-001 Go to Project
Environmental Assessment (EA) - Complete
This is a study titled "The Theory and Practice of Perpetual Care of Contaminated Sites" by Dr. Joan Kuyek, submitted by Alternatives North. The summary of this study is available on this web page in a seperate file.
This is a covering letter from Alternatives North for a study of perpetual care of contaminated sites by Dr. Joan Kuyek. The study summary is included in the same file.
This is a Note to File describing a meeting with the developer regarding new subsidence of the B1 pit wall and possible new activities on the Giant site.
Prairie Creek Mine - EA0809-002 Go to Project
Environmental Assessment (EA) - Complete
This is a letter from the Review Board to Canadian Zinc Corporation on project design modifications to the Prairie Creek Mine.
Review Board response to Parks Canada
(925.7 KB)
WQO approach and final submissions
(127.2 KB)
NICO Project - EA0809-004 Go to Project
Environmental Assessment (EA) - Complete
This is a letter from the Review Board that provides instructions on party status applications and information requests along with respective deadlines.
Work Plan updated July 15, 2011
(295.1 KB)
DAR conformity determination
(42.47 KB)
Gahcho Kue Diamond Mine - EIR0607-001 Go to Project
Environmental Impact Review (EIR) - Complete
This is part of De Beers' conformity response to Item 1 regarding water quality and phosphorus in Kennady Lake.
This is part of De Beers' conformity response to Item 1 regarding water quality and phosphorus in Kennady Lake.
This is part of De Beers' conformity response to Item 1 regarding water quality and phosphorus in Kennady Lake.
This is part of De Beers' conformity response to Item 1 regarding water quality and phosphorus in Kennady Lake.
Appendix_8.IV_CEB_2011_Conformity_Respns_15Jul11
(346.71 KB)
Appendix_8.V_DO_2011_Conformity_Respns_15Jul11
(158.42 KB)
Appendix_9.I_2011_Conformity_Respns_15Jul11
(936.23 KB)
Appendix_9.II_2011_Conformity_Respns_15Jul11
(501.44 KB)
This is part of De Beers' conformity response to Item 1 regarding water quality and phosphorus in Kennady Lake.
This is part of De Beers' conformity response to Item 1 regarding water quality and phosphorus in Kennady Lake.