The project consists of the construction, operation and closure of a 180 km all season access road from the Prairie Creek Mine (km 0) to the Liard Hwy (km 180). The route is currently winter only but has not been used since 1982. There are some realigned sections from the winter road. All season road construction is proposed over 3 years, with an operating life of 17 years followed by road closure and reclamation. Km 17 to 100 are in Nahanni National Park Reserve with the balance on territorial lands and a small segment on federal land.
The 2025 Annual Environmental Assessment Measures Report for Canadian Zinc Corporation Ltd.’s Prairie Creek All-Season Road Project summarizes the GNWT’s actions between July 1, 2024, and June 30, 2025.
Parks Canada Agency is submitting Implementation of the Canadian Zinc Corporation All-SeasonRoad Environmental Assessment Measures– PCA 2025 Annual Report for EA1415-01, for the period of
July 1, 2024 to June 30, 2025.
Prairie Creek All Season Road EA 1415-01 Measure 15-2: Annual Reporting from the Developer
| New | Total | Stage |
|---|---|---|
| 1 | Preliminary screening | |
| 4 | Assessment/review startup | |
| 30 | Scoping | |
| 20 | Terms of Reference and workplans | |
| 94 | Developer's Assessment Report/Environmental Impact Statement | |
| 126 | Information requests | |
| 96 | Technical or community sessions | |
| 99 | Technical reports | |
| 65 | Public hearings | |
| 13 | Hearing follow-up | |
| 4 | Report of Environmental Assessment/Impact Review | |
| 62 | Post Report materials | |
| Minister's decision and final measures (current stage) | ||
| 6 | Other public registry materials | |
| 0 | 620 | Total Documents (See All) |