Letter Selwyn Chihong to MVEIRB re pause in work
(141.45 KB)
Letter from Selwyn Chihong Mining Limited re pause in work on Developer's Assessment Report.
Note to file - HPAR project update
(162.28 KB)
Sahtu Landu Use Planning Board conformity determination for the Howard's Pass Access Road Upgrade project
Note to File Meeting with Selwyn_12.05.2016
(344.63 KB)
Interim HPAR Upgrade Project Workplan
(127.03 KB)
Reasons for Decision on the Scope of EA
(291.61 KB)
This is the Review Board's Terms of Reference for the Howard's Pass Access Road Upgrade Project EA.
This is the Review Board's cover letter for the Terms of Reference, the Reasons for Decision on the Scope of EA, and the interim work plan.
Review of the Draft ToR, ORS material
(1.75 MB)
Additional comments from the developer on reviewer comments and Review Board staff responses.
Letter from the Naha Dehe Dene Band to the MVEIRB regarding the draft Terms of Reference for EA1516-01
Note to File - Change in Personnel
(299.54 KB)
The Review Board has issued the Draft Terms of Reference. The document is open for review from parties and the developer on the Online Review System.
Note to File, Draft ToR
(128.87 KB)
This document contains the reviewers comments on the DPToR, the developer's responses, and Review Board staff responses.
Letter from Environment and Climate Change Canada acknowledging receipt of Notification pursuant to SS.79(1) of the Species at Risk Act
HPAR ToR Review Comment Table Jan 25 2016v2_SCML
(863.64 KB)
This note to file is for the WCS letter dated Jan. 22, 2016 regarding clarrification of its comments on the Developer's Proposed Terms of Reference.
A letter from the Wildlife Conservation Society regarding clarrification of comments on the Developer's Proposed Terms of Reference.
Note to file describing extension for the Developer to respond to parties' comments on the DPToR. New deadline is January 25th, 2016.
Selwyn has requested an extension to provide responses to parties comments on the DPTOR.
Note to File_Extension for DPToR responses
(357.97 KB)
GNWT letter to Kaska Dena Council regarding participation in EA1516-01, Howard's Pass Access Road Upgrade Project
HPAR Community Scoping Session Summary
(1.56 MB)
Annex A- Attachment to MVLWB letter to SLUPB
(122.45 KB)
Letter from the Mackenzie Valley Land and Water Board to the Sahtu Land Use Planning board requesting that the SLUPB conduct a conformity check of the HPAR upgrade project with the SLUP.
This letter from the Review Board to the MVLWB is a follow up to the GNWT's letter to the MVLWB, and others, dated Nov 13, 2015 regading a conformity determination agaisnt the Sahtu Land Use Plan.
Update on scoping dates in Ross River and Watson Lake for the Howard's Pass Access Road upgrade project.
Update on Nahanni Butte community scoping sessions for the Howard's Pass Access Road upgrade project environmental assessment
Letter from the GNWT regarding the Howard's Pass Access Road Upgrade project and conformity with the Sahtu Land Use Plan
Document showing changes between original and updated version of the Developer's Proposed Terms of Reference. This document is available for review on the online review system
Note to File-Extension for DPToR comments
(302.67 KB)
Updated version of the Developer's Proposed Terms of Reference which includes changes to Section 7, Section 3.2,and Section 8.
Technical Scoping Session Summary
(1.35 MB)
Nahanni Butte Scoping Session Agenda
(162.42 KB)
Norman Wells Scoping Session Agenda
(160.58 KB)
Tulita Scoping Session Agenda
(501.88 KB)
Developer's Scoping Presentation
(2.29 MB)
This is the developer's presentation for the Yellowknife scoping session.
Letter from Canada to Aboriginal Groups
(243.99 KB)
Agenda for the Yellowknife Scoping Session
(161.07 KB)
Updated dates and locations for the HPAR technical and community scoping sessions
Letter to SCML DPToR submission 092215
(100.82 KB)
A letter from YESAB in response to the Review Board's September 11 letter regarding cooperation on EA.
A letter from the Review Board to the Yukon Environmental and Socio-economic Assessment Board regarding notification of referral of the Howard's Pass Access Road project to EA.
This is volume 3 part 2 of the appendices to the project description report submitted by the developer to the MVLWB and Parks Canada.
This is part one of the appendices to the project description report submitted by the developer to the MVLWB and Parks Canada.
05 Volume 2 - Project Description Report
(13.73 MB)
This is volume one part four of the water licence and land use permit applications submitted by the developer to the MVLWB and Parks Canada.
This is volume one part three of the water licence and land use permit applications submitted by the developer to the MVLWB and Parks Canada.
This is volume one part two of the water licence and land use permit applications submitted by the developer to the MVLWB and Parks Canada.
This is volume one of the water licence and land use permit applications submitted by the developer to the MVLWB and Parks Canada.
Letter of referral from Parks Canada
(49.06 KB)
SARA notification letter to EC
(184.52 KB)
A letter from the Review Board to the public regarding referral of the project.
Letter from the Review Board to the Developer
(146.98 KB)