geotechnical survey
There are no documents at this time.
This is the Review Board's response to the Oct. 9, 2009 letter from INAC regarding the Imperial Dehcho Geotechnical Program (EA 03-009).
This letter from INAC describes the Ministerial decision regarding the environmental assessment of the Imperial Dehcho Geotechnical Program (EA 03-009). It follows post-Report of Environmental Assessment consultations. Attachments include revised measures and a letter dated April 3, 2008 from Pehdzeh Ki First Nation.
MVEIRB letter to Minister Prentice expressing concerns over the length of time and the process for the "Consult to Modify" and decision-making process on the EA.
DIAND has suggested a modification to Measure 13 in the IOL Geotechnical Program Report of Environmental Assessment and asks if PKFN has any concerns with the proposed wording.
Formal clarification that the Review Board's Jan. 27, 2006, Reasons for Decision were intended to update parties about the "consult to modify" process, and not to amend the Report of Environmental Assessment.
Letter in response to the changes proposed by the Responsible Ministers to the measures in the Report of Environmental Assessment for the Imperial Geotechnical Program assessment.
Letter offers additional information to supplement recommendations made by the Responsible Ministers during the consult to modify process for Imperial Oil's proposed geotechnical field investigation program, Dehcho region.
Letter is the SKFN's response to proposed modifications to measures contained in the Report of Environmental Assessment for Imperial Oil's proposed geotechnical field investigation program, Dehcho region.
Submitted for Imperial Oil's proposed geotechnical field investigation program, Dehcho region. Also serves as the outline for the DAS' hearing presentation.
Letter discusses and responds to correspondance sent by the developer to the Minister regarding Imperial Oil's proposed winter field geotechnical investigation program, Dehcho region.
Letter initiates the consult to modify process for Imperial Oil's proposed geotechnical survey in the Dehcho region.
Letter is in response to the Report of Environmental Assessment issued by MVEIRB for the developer's proposed winter field geotechnical investigation program, Dehcho region.
For Imperial Oil's proposed geotechnical field investigation program, Dehcho region.
Confirmation of receipt of the REA for Imperial Oil's proposed winter field geophysical investigation program, Dehcho region.
Report of Environmental Assessment
(2.71 MB)
Letter constitutes the developer's final comments and responses in the environmental assessment of Imperial Oil's proposed geotechnical field investigation program, Dehcho region.
Response to IRs issued in the environmental assessment of Imperial Oil Ventures' Geotechnical program.
Response to a information request arising from the community hearing in Fort Simpson for Imperial Oil's proposed geotechnical field investigation program, Dehcho region.
The Request for Ruling arose from discussions at the community hearing held in Fort Simpson for Imperial Oil's proposed geotechnical field investigation program, Dehcho region.
An IR arising from the community hearing in Fort Simpson issued to the GNWT in the environmental assessment of Imperial Oil's proposed geotechnical field investigation program, Dehcho region.
| New | Total | Stage |
|---|---|---|
| 3 | Preliminary screening | |
| 21 | Assessment/review startup | |
| 2 | Scoping | |
| 9 | Terms of Reference and workplans | |
| 9 | Developer's Assessment Report/Environmental Impact Statement | |
| 14 | Information requests | |
| Technical or community sessions | ||
| 6 | Technical reports | |
| 23 | Public hearings | |
| Hearing follow-up | ||
| 3 | Report of Environmental Assessment/Impact Review | |
| 9 | Post Report materials | |
| 2 | Minister's decision and final measures (current stage) | |
| 4 | Other public registry materials | |
| 0 | 105 | Total Documents (See All) |