Oil and gas exploration project at Summit Creek, Sahtu region, NWT
There are no documents at this time.
MVEIRB thanks SLWB for bringing the proposed changes to their attention and confirms details of a phone conference earlier that week. MVEIRB also provided suggested measure and guidance for the amendment to the LUP
Northrock would like to amend their LUP to allow for a winter airstrip to support construction.
Notes of all issues and topics covered in the meeting.
Northrock's winter workers appeared to be using water from the Stewart Lake to make snow and this was lowering the level of the lake and effecting peopleƒ_Ts ability to harvest fish. This was being done against the request that no water be used from that
Sahtu Land and Water Board has decided to approve Northrocks application for LUP and WL.
NEB as the designated regulatory agency has decided to adopt MVEIRB's recommendations.
Letter from INAC to MVEIRB
(172.85 KB)
Report of Environmental Assessment
(2.16 MB)
INAC will not be submitting a Technical Report on the Summit Creek project as it stands.
Maps and Cultural/Heritage Information on the Proposed Study Area.
Distribution of IR's and Responses
(5.24 MB)
Northrock's response to IR 1.2.1
MVEIRB confirms receiving CPAWS IR and informs them that their IR will be issued to Northrock
David Etchinelle is concerned with his ability to continue harvesting in the area around Stewart Lake because of the Northrock's proposed development.
CPAWS submission of IR's for the proposed Summit Creek Project.
More responses from Northrock to IR's Submitted by MVEIRB.
Sahtu Renewable Resources Board's response to MVEIRB's IR
Northrock's response to MVEIRB's IR.
Distribution of MVEIRB's Information Requests and confirmation of directly affected parties.
MVEIRB contacted SLUPB to see if they wished to have directly affected party status.
| New | Total | Stage |
|---|---|---|
| 3 | Preliminary screening | |
| 5 | Assessment/review startup | |
| Scoping | ||
| 8 | Terms of Reference and workplans | |
| 4 | Developer's Assessment Report/Environmental Impact Statement | |
| 9 | Information requests | |
| Technical or community sessions | ||
| Technical reports | ||
| 5 | Public hearings | |
| Hearing follow-up | ||
| 1 | Report of Environmental Assessment/Impact Review | |
| 2 | Post Report materials | |
| 2 | Minister's decision and final measures | |
| 10 | Other public registry materials | |
| 0 | 49 | Total Documents (See All) |