This reference document provides a single point of contact for links to the developers Project Description Report and Appendices in order as they appear in the hard copy.
Developer's covering letter for WLWB application.
Traditional Knowledge study for the proposed Whati all-season road, prepared by the Tlicho Government in 2014
This document contains preliminary screening material from the WLWB and is a compilation of the ORS table of comments and responses as well as attached documents from reviewers and the developer..
Completed WLWB application form.
Wek'eezhii Land and Water Board draft land use permit and terms and conditions for the Tlicho All-season Road.
Draft emergency response plan (ERP) for construction of the all-season road, prepared by the GNWT
Archaeological site chance find protocol (GNWT-DOT)
Draft fish and fish habitat protection plan (FFHPP)
Erosion and sediment control manual (GNWT-DOT)
Micro-economic analysis of the all-season road prepared by the Community Government of Whati in 2015
Archaeological impact assessment (AIA) prepared by Stantec for GNWT-DOT in 2014
DFO fisheries protection self-assessment record, prepared by GNWT-DOT
Hydrological study progress report prepared by Stantec for the GNWT-DOT
Hydrologic and hydraulic study prepared by Stantec for GNWT-DOT
Field survey photos from argo trip along the proposed all-season route in June 2014, including summary table and cooridinates of observations
All-season road alignment map and images prepared by Kavik-Stantec for GNWT-DOT
Email correspondance confirming that the community of Whati will permit refuse from construction camps in the Whati landfill
Draft Waste Management Plan (WMP)
Draft Wildlife and Wildlife Habitat Protection Plan
Draft Spill Contingency Plan
Draft Quarry operations plan, prepared by GNWT-DOT
Table characterizing granular and bedrock features (with recommendations for future work) by section along the all-season road
Conceptual designs of the major bridge and culverts along the all-season road, prepared by GNWT-DOT
Powerpoint photo presentation of existing conditions along the proposed all-season road route
A map and route plan and profile (by route section) prepared by DOT of the proposed all-season road to Whati
A letter from Tlicho Grand Chief Eddie Erasmus to the Minister of DOT regarding collaboration with DOT on preparing studies for an application for an all-season road
Engagement summaries, archival information and other engagement records referenced in the Project Description Report.
Log of engagement activitied undertaken by the GNWT - DoT.
Introduction to Appendix E of the Project Description Report, including affected parties, engagement goals and methods, engagement plan, and engagement summary and log templates.
Tlicho Government and Community Government of Whati Commitments.
An economic cost benefit analysis quantifying community and industry costs and benefits associated with the Tlicho All-season Road project.
TASR figures including road alignment, road cross section, alternative routes, borrow areas, surficial geology. soils, ecozones, burn areas and land uses.
Scoping study of potential social, economic and cultural benefits and risks of a proposed all-weather road in the community of Whati.
Description of water sampling procedure at SNP sites.
Appendix A to the Project Description Report. Joint letter to acknowledge access through an agreement between the Tlicho Government and the Government of the Northwest Territories.