Fuel Cache Retrieval and Clean-up development - EA00-002 Go to Project
Environmental Assessment (EA) - Complete
Information Request Response
(241.85 Ko)
Report done by Public Works and Government Services Canada and originally submitted to the Department of Indian Affairs and Northern Development. Regarding the Site Investigation of the Fuel Cache site.
Developer's Assessment Report
(16.04 Ko)
Note to File
(31.82 Ko)
Letter from MVEIRB to CZN re: EAR
(40.73 Ko)
Letter from DIAND to MVEIRB re: IR timeline
(21.99 Ko)
Pine Point Area Timber Harvest Proposal - EA00-005 Go to Project
Environmental Assessment (EA) - Complete
Terms of Reference and Work Plan
(2.09 Mo)
RWED's final comments on the terms of reference and work plan for the Patterson Sawmill's cutting permit.
DIAND's final comments on the terms of reference and work plan for the Patterson Sawmill's cutting permit.
RWED's comments on the Terms of Reference and Work Plan for the Patterson Sawmill EA.
Environment Canada's comments on the Draft Terms of Reference and Work Plan for the Patterson EA.
Natural Resources Canada informs MVEIRB that they are not a responsible minister, but they could act as an Expert Advisor during the EA.
INCA confirms that they do have comments on the draft terms of reference but they will not be able to make the deadline.
GNWT dose have comments on the draft terms of reference but will not be able to submit them by the January 22nd deadline.
DFO's response to the draft terms of reference and work plan.
The Enterprise Settlement Council is concerned with the short time for review of and comments on the draft terms of reference.
Cameron Hills Exploratory Drilling Project - EA00-004 Go to Project
Environmental Assessment (EA) - Complete
The amendment request was approved subject to further consideration in the cumulative impacts section of the Cameron Hills EA.
NEB has no concerns with Paramount's request
EC does not agree that inclusion of 10 possible future wells should be included in final terms since information is lacking.
The removal of references to existing wells for the Cameron Hills project is valid since the wells are covered under existing Land Use Permits and therefore not required as part of the current LUP application.
Paramount request for Draft TOR addition
(111.62 Ko)
Request for comments on proposed amendment.