Main Content
Onglets principaux
Results
Displaying 4676 - 4700 of 12221
Gahcho Kue Diamond Mine - EIR0607-001 Go to Project
Environmental Impact Review (EIR) - Complete
This is the presentation for Nov 30th - Day 3 of the EIS Analysis Session on the topics of Air, Land and Wildlife.
This letter to parties describes in detail how to participate remotely in the upcoming EIS Analysis session.
EIS Analysis session- Remote Participation
(211.26 Ko)
Agenda- GK EIS Analysis Sessions
(397.89 Ko)
Nechalacho Rare Earth Element Project - EA1011-001 Go to Project
Environmental Assessment (EA) - Complete
The following document lists the Review Board's Information Requests for Avalon Rare Metals Inc.'s Thor Lake Rare Earth Element Project.
The following document is a cover letter to Avalon Rare Metals Inc. regarding the Review Board's information requests for Avalon's Thor Lake Rare Earth Element Project.
The following document is an updated Workplan for the environmental assessment of Avalon Rare Metals Inc.'s Thor Lake Rare Earth Element Project.
The following document lists the results of a 2011 feasibility-related groundwater quality study Avalon Rare Metals Inc. conducted at the proposed Thor Lake Rare Earth Element Project site.
Yellowknife Gold Project (2008) - EA0809-003 Go to Project
Environmental Assessment (EA) - Ongoing
This is a note to file to clarify a document posted by the Review Board on November 15, 2011 regarding application for party status in teh Tyhee Gold environmental assessment.
Request for party status-Tyhee Gold Project EA
(125.76 Ko)
Mineral Exploration Program - EA0506-005 Go to Project
Environmental Assessment (EA) - Cancelled
This is the letter of transmittal for the Reasons for Decision on the further consideration of measures in the 2007 Report of EA
This is the Reasons for Decision for further consideration of measures from the 2007 Report of Environmental Assessment of the Encore Renaissance Resources Corp. proposed mineral exploration program in Drybones Bay, NT.
Giant Mine Remediation Project - EA0809-001 Go to Project
Environmental Assessment (EA) - Complete
This is a cover letter for the undertakings from the Giant Mine Technical Sessions.
This document is Undertaking #12 from the Giant Mine Technical Sessions held on October 17 to 21,2011.
This document is Undertaking #11 from the Giant Mine Technical Sessions held on October 17 to 21,2011.
Giant Mine Technical Session Undertaking 10
(450.46 Ko)
This document is Undertaking #8 from the Giant Mine Technical Sessions held on October 17 to 21,2011.
This document is Undertaking #7 from the Giant Mine Technical Sessions held on October 17 to 21,2011.
Giant Mine Technical Session Undertaking 5
(594.4 Ko)
Giant Mine Technical Session Undertaking 3 and 9
(826.52 Ko)
Giant Mine Technical Session Undertaking 2 and 4
(579.41 Ko)
This document is part (c) of Undertaking #1 from the Giant Mine Technical Sessions held on October 17 to 21,2011.
This document is part (b) of Undertaking #1 from the Giant Mine Technical Sessions held on October 17 to 21,2011.
This document is part (a) of Undertaking #1 from the Giant Mine Technical Sessions held on October 17 to 21,2011.
NICO Project - EA0809-004 Go to Project
Environmental Assessment (EA) - Complete
GNWT response to Tlicho Government IR 32
(94.71 Ko)