Giant Mine Remediation Project - EA0809-001 Go to Project
Environmental Assessment (EA) - Complete
This letter provides Alternatives North's views on the YKDFN request for an extension.
The following document is a report from a joint Alternatives North/Yellowkives Dene First Nation workshop on independent oversight for AANDC's Giant Mine Remediation Project.
Request from NSMA regarding hearing notification
(108.31 Ko)
YKDFN letter re: Mill Conveyor
(134.37 Ko)
This letter from the Review Board asks the Giant Team for the legal basis for the mill conveyor work and other any other site stabilization activties that are within the scope of the ongoing environmental assessment
Letter to Parties re YKDFN extension request
(433.64 Ko)
These attachments to the March 13 2012 letter from the developer were received on March 21 2012. They provide additional technical details about the mill conveyor work.
Gahcho Kue Diamond Mine - EIR0607-001 Go to Project
Environmental Impact Review (EIR) - Complete
IR responses to NSMA
(165.89 Ko)
IR responses to EC and GNWT
(213.36 Ko)
IR response to TC 03: Figure TC-03-2
(6.39 Mo)
IR response to TC 03: Figure TC-03-1
(5.63 Mo)
IR responses to Transport Canada
(1.18 Mo)
IR responses to Parks Canada
(55.52 Ko)
Project update and proposed technical meetings
(229.59 Ko)
This is the first of 5 Supplemental Monitoring documents submitted by De Beers.
Nechalacho Rare Earth Element Project - EA1011-001 Go to Project
Environmental Assessment (EA) - Complete
The following document is a response from Avalon Rare Metals Inc. to a 22-Mar-12 Review Board clarification letter regarding the Thor Lake Rare Earth Element Project.
The following document is a letter from the Review Board to Avalon Rare Metals Inc. clarifying Avalon's information request responses related to the environmental assessment of Avalon's Thor Lake Rare Earth Element Project.
Yellowknife Gold Project (2008) - EA0809-003 Go to Project
Environmental Assessment (EA) - Ongoing
IR 1-1-6 Water Balance
(38.58 Ko)
Part 1 Key Line of Inquiry IR 1-1-5. Water quality issues related to existing impacts from discovery mine- cumulative effects.
Part 1 Key Line of Inquiry- IR 1-1-4 Water quality monitoring and adaptive management.
IR 1-1-3 Effluent Treatment Options
(74.92 Ko)
IR 1-1-2 Cyanide attenuation
(70.68 Ko)
IR 1-1-1 with Tables
(79.17 Ko)
IR 1-2-5 Traffic Volumes.Table
(54.23 Ko)
This is the cover letter to the remaining IR responses from Part 1- Key Lines of Inquiry and Part 2-Other Issues IR 1-2-5 Traffic volumes. The seperate IR documents will follow.